What happens if a hold point is not communicated to the source inspector (SI)?

Get more with Examzify Plus

Remove ads, unlock favorites, save progress, and access premium tools across devices.

FavoritesSave progressAd-free
From $9.99Learn more

Prepare for the API SIFE Source Inspector Test with focused flashcards and numerous multiple choice questions, complete with detailed hints and explanations. Ready yourself for the certification exam!

If a hold point is not communicated to the source inspector (SI), the situation typically leads to the issuance of a nonconformance against the supplier/vendor. A hold point is a specific stage in the project at which the work must stop until the source inspector can assess the work to ensure compliance with quality standards or specifications. When this communication does not occur, it indicates that the necessary oversight was missed, which compromises the integrity of the process or product. As a result, a nonconformance is documented to formally acknowledge the failure to adhere to the established protocols, allowing for corrective actions to be taken and ensuring accountability in the quality assurance process.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy